"Big Tu" cameo at the EC meeting. Laid out the framework for the land delivery of the high-speed rail project connecting 3 airports to the end. "CP Joint Venture" signed the project on October 15, in the area of ​​1 year contract for "Sak Siam", if successful Considered as the magnum opus of the "Prime Minister" compared to "Pao Prem" with "Eastern Seaboard".

On 30 September 62, Gen. Prayut Chan-o-cha, Prime Minister and Minister of Defense, chaired a meeting of the Eastern Special Development Zone Policy Committee, or the PM, with the meeting acknowledging the schedule of land delivery to Completed quickly In the high-speed rail project connecting 3 airports, which are ready to deliver land 72%. In addition, the Ministry of Energy has urged the Ministry of Energy to accelerate the removal of 12 kilometers of gas pipelines, lifting 16 high-voltage electricity transmission posts, and the Ministry of Interior accelerating the move of sewers Large size 4 points, move high voltage transmission pole 14 kilometers, lift high voltage transmission pole 39 points, move large water supply pipe 2 kilometers long

While the Ministry of Transport, by the SRT, has used the right to expedite the relocation of private oil pipes of 44 kilometers, including the expedition of the Land Exemption Decree B.E. .. which will make the delivery of the project area in accordance with the plan and the construction project. Complete the target

Mr. Worawut Mala, Acting Governor of the State Railway of Thailand Confirm that the delivery of land Will accelerate the process within 1 year as specified. In addition to solving the problem of compromised areas There is still an underground utility. That must be coordinated with relevant departments Let's proceed to make a joint demolition plan, whether the Electricity Generating Authority Metropolitan Electricity Authority Metropolitan Waterworks Authority, Bangkok. The private sector by this week will be invited to discuss all To determine the plan And all timlines Which was presented to Kor. Acknowledged. As well as having to expedite the drafted Land Act

Mr Kanit Saengsuphan, Secretary General of the Ministry of Energy confirmed that the SRT does not have a problem with the delivery of the area. But concerned about the area of ​​other related agencies Which the Office of the Auditor General has assigned all relevant departments Complete the plan together with the railway within 1 week to reach a conclusion. Including to consider the budget for the operation After that, prepare to talk to the private sector to acknowledge the delivery of the area before October 15.

For U-Tapao Airport Development Project And the Eastern Aviation Authority, Mr. Kanit revealed that the Administrative Court agreed with the selection committee and the appeal of KorPhor. Not accepting 2 documents (Business proposal proposal box And the Financial Compensation Box) of the Than Holding Joint Venture Group, which the Company submitted to the Supreme Administrative Court on 16 September 2019.However, the selection committee will proceed by determining the technical documentation. Finish by October 9, 2019 and open the envelope to find a contract negotiator. Which is expected to be completed by October 2019

While Mr. Sak Siamchitchai, the Minister of Transport, said that the meeting agreed with the results of negotiations under the framework of inviting private investment (RFP) and issued a letter calling the employer to sign. Which will have the condition that How will the delivery be? The first year as soon as signing, 70 percent After that, the relevant departments regarding the migration of public utilities Which has a period of 18 months, must inform whether or not to finish But if not done We also have the opportunity to extend the time. Without giving compensation But trying to finish And this must be done immediately The small board of this story will oversee In truth, he had already discussed it. Only did not do anything officially. After the joint venture group, Charoen Pokphand Holding Company Limited and CPH were able to bid, he had to take various risks. Spontaneous Which is according to the RFP

When asked if he had agreed to this issue without any problems Mr Sak Siam said that there is nothing more Have to wait and see, on October 15, CPH will sign the contract When asked if there would be nothing to delay the signing again Mr Sak Siam said that we have fully negotiated in accordance with the RFP framework. Therefore, it is a matter that the employer must issue a letter dated the date of signing the contract. Which is a normal principle in proceeding with the state

When asked whether the Prime Minister was particularly concerned about this matter or not Mr Sak Siam said that the prime minister only said that Go and see carefully that the plan is to deliver the area. Ask to take action that will not be a private burden. But at the same time, if there are really limitations We then extend the time not to adjust. When asked about this, the government tried to facilitate the private sector to the full. Mr Sak Siam said that the government actually wants this to be successful. Not only the high-speed rail connecting these 3 airports, but every issue in the EEC area, so these things will give foreign investors confidence. And hope everything goes smoothly Because this project is an important project of Thailand And if this project is successful, it is considered the prime minister's masterpiece. If compared, during the period of General Prem Tinsulanonda's government, there would be a Eastern Seaboard project. But nowadays there is an EEC project that is considered the work of the Prime Minister.

read more…